APPROACH
QUALITY | time | COST
BALANCING EXPECTATIONS and CONSTRAINTS through a clear, step-by-step design process.
A solution just for you.
Blends functionality, attention to detail, and sustainability.
QUALITY
-
FUNCTION
We design well designed spaces that integrate and respond to their surroundings.
This fosters human connection and enhances well-being, having impacts felt beyond construction.
-
ATTENTION
We recognize that every project has unique challenges that need specific attention.
Dedicated time to the planning and design phase saves time and money in the long run.
-
SUSTAINABILITY
A commitment to urban infill, using Passive House strategies, and being highly selective about building materials results in:
A reduction in carbon footprints and an increase in healthy living spaces.
TIME
Planning + design have an impact of a lifetime.
A six phase design process guides projects toward completion
COST
Budget with realistic expectations.
These numbers provide a basic range for a simple ADU project. Actual costs depend on a project's size and complexity. These numbers can be used to begin your project planning.
PRE-CONSTRUCTION
$50,000 to $85,000
Required for Submittal
Architectural | $30,000
Structural | $10,000
Energy Analysis | $1,000
Permits + Fees | $10,000
As Needed
As Builts | $1,200
Civil Survey | $5,500
Grading + Drainage | $3,000
Arborist | $2,200
Green Building | $3,000
Interior Design | $5,000
Landscape Design | $6,000
EV Plans | $1,500
Printing | $500
CONSTRUCTION
$300,000 to $850,000
Construction Costs
Infrastructure
Demolition
Trenching
Foundation +Framing
Roofing
Flashing + Gutters
Windows, Doors, Skylights
Insulation, Mechanical
Electrical + Plumbing
Drywall + Paint
Fixtures + Finishes
Construction Management
Supervision + Cleanup
Overhead + Profit
Actual estimate by contractor
TOTAL PROJECT COST
$350,000 to $900,000
Additional Costs
Consider potential additional costs before starting.
Additional Home Improvements + Deferred Maintenance (only you know what these are) $300,000
Site Improvements
Electrical Upgrade $15,000
Sewer Lateral Replacement $10,000
Solar Installation $50,000
Landscaping, Hardscape, Fence + Carports $75,000
Fixture + Finish Upgrades $65,000